RIL repairing three shut wells at KG D6 to raise gas output

Having reversed a decline in gas output at KG-D6 by starting a new production well, Reliance Industries is repairing three shut wells on the main fields in the block and will take up a similar number later to further improve output.

RIL and partner BP plc are carrying out remedial action to stop water ingress from choking wells even as the first production well on the block in more than four years ramped up output by over 15 per cent to 13.7 million standard cubic meters per day.

"We can't drill any more wells on (main) Dhirubhai 1 and 3 (D1&D3) fields," RIL Executive Director P M S Prasad told reporters here.

The D1&D3 fields have proved to be less prolific than previously anticipated, forcing RIL to downgrade the recoverable reserves to 2.9 trillion cubic feet (tcf) from 10.03 tcf estimated in 2006. Of this, about 2.2 tcf has already been produced and RIL expects the remaining 0.75 tcf could be extracted through existing wells.

"We are currently doing workovers on three shut wells," Prasad said.

Of the 18 wells on D1&D3, 10 were shut due to water and sand seeping in. The two partners are currently attempting to cut off water ingress into three wells. If successful, they will carry out this work on a similar number of wells in 2015.

In between, they will install a compressor at the onshore terminal to pull gas up from wells that are over a kilometre below the sea.

"Workovers are fraught with risk so we have to see the result of the current workovers," he said.

On the MA field, also in KG-D6 block, RIL-BP added the MA-8 well on January 2 and plan to drill a branch well (called side tracking) later this year by re-entering a shut well.

This well will add up to 2.5 mmscmd to production. D1&D3 produce about 8.5 mmscmd and the rest of the current KG-D6 output of 13.7 mmscmd comes from MA.

BP India head Sashi Mukundan said, "This is part of the next phase of producing the gas in the MA field after the oil has been produced."

A similar side-track well is planned on D1&D3 in 2015 and another one may be looked at on MA in 2015 if the results of the one planned this year are successful, he said.

"We are currently doing water shut-off job on three wells on D1&D3 gas fields before we install a compressor in the first half of 2015," he said.

The KG-D6 fields had become India's largest producing gas fields in March 2010 but in less than a year it witnessed unanticipated water and sand ingress shutting down well after well.


  • Everybody who contributes to India’s economic growth must be paid well

    Private sector blue chip companies are known to pay top dollar for top-level talent. Directors in such companies take home hefty pay packets.


Stay informed on our latest news!


Sarthak Raychaudhuri

vice-president, HR, Asia South Whirlpool of India

GV Nageswara Rao

MD & CEO, IDBI Federal Life

Timothy Moe

Goldman Sachs


Amita Sharma

Smart cities for the smart citizens

The 21st century has been spoken of as the urban ...

Zehra Naqvi

The prejudiced childhood

Sometimes the most unusual things can remind you of the ...

Bubbles Sabharwal

Women of the world, unite for a change

Last week I attended the Women in the World forum ...


William D. Green

Chairman & CEO, Accenture