3 rail links to transport coal delayed; CIL output to be hit

Tags: News
The delay in the schedules for completion of three critical rail links for transporting coal from CIL mines is likely to impact the company's production by 67.16 million tonnes over the next two years.

State-owned Coal India Ltd (CIL), which accounts for over 80 per cent of the domestic coal production, is already drawing flak for missing its production targets.

According to an official document, the Railways has indicated "the revised timelines for these three critical rail projects".

It said: "The timeline indicated for Tori-Shivpur was December 2016 as against March 2015; for Jharsugudu-Barpalli June 2016 against December 2014 approved earlier. For Bhupdevpur-Korichapar, Railways indicated timeline as September 2016."

The impact of the delay is envisaged at 67.16 million tonnes (MT), of which 13.6 MT will be in 2015-16 and 16.1 MT in 2016-17 in the case of Tori-Shivpur line and 12.5 MT in 2015-16 and 20 MT in 2016-17 in the case of Jharsugusa- Barpalli, it said.

There has been a revision in the schedule by 21 months in the case of Tori-Shivpur and 18 months for Jharsuguda-Barpalli when compared to the initially decided timelines by the Cabinet Committee on Investment, it said.

"In case of Bhupdevpur-Korichapar, if this line does not come up by 2015-16, the loss of production is envisaged to be at 4.96 million tonnes from the mines of CIL alone," it added.

Tori-Shivpur-Kathuatia Railway line (90.7 KM) is in North Karanpura in Jharkhand, Jharsuguda-Barpalli-Sardega Railway line (53 km) in IB Valley, Odisha and Bhupdevpur-Korichapur- Dharamjaigarh (180 km) in Mand-Raigarh Coalfield, Chhattisgarh.

According to the decision of CCI in its meeting held in July last year, the Tori-Shivpur-Kathautia Railway line was to be completed by March 2015 and Jharsuguda-Barpalli-Sardega Railway Line by December 2014. For Bhupdevpur-Korichapar- Dharamjaigarh Railway Line, the Ministry of Railways was to indicate timelines for the completion.

CIL produced 462 MT coal in FY'14, missing the target of 482 MT. In FY'13, the company produced 452.5 MT coal while the target was 464 MT.

Post new comment

E-mail ID will not be published
CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.

EDITORIAL OF THE DAY

  • Bureaucrats have enjoyed flying miles at taxpayer expense for too long

    The beleaguered Indian taxpayer will certainly applaud prime minister Narendra Modi’s attempt to deliver on his promise of cutting down fiscal defic

FC NEWSLETTER

Stay informed on our latest news!

INTERVIEWS

GV Nageswara Rao

MD & CEO, IDBI Federal Life

Timothy Moe

Goldman Sachs

Chander Mohan Sethi

CMD, Reckitt Benckiser India

COLUMNIST

Varun Dutt

<b>Riskfactor</b>: CHAIN REACTION

A domino effect is the cumulative effect produced when one ...

Zehra Naqvi

Rememberance and forgetting are crucial

Memories are so vital to our lives that they can ...

Dharmendra Khandal

Sandalwood may get extinct if not protected

When we talk of sandalwood, the most common usage that ...

INTERVIEWS

William D. Green

Chairman & CEO, Accenture