Boiler light up at RPower's Sasan UMPP becomes functional

Reliance Power's equipment for the fourth unit of its Sasan ultra mega power project

RELATED ARTICLES

in Madhya Pradesh has started functioning.

The boiler light up has been achieved in respect of the fourth 660 MW unit of the 3,960 MW (6X660 MW) Sasan Ultra Mega Power Plant (UMPP) being developed by Sasan Power Limited, a wholly owned subsidiary of the company, Reliance Power said in a BSE filing.

The first 660 MW unit of the Sasan UMPP was commissioned in March 2013 and the second in January 2014 and the third unit became operational last month.

Coal production has already commenced from the 20 million tonnes Moher and Moher-Amlohri coal mines associated with the power project.

Reliance Power has 3,205 MW power generation capacity, including 3,120 MW of thermal and 85 MW renewable energy sources.

Shares of Reliance Power were trading at Rs 73.20, up 2.02 per cent on the BSE.

Post new comment

E-mail ID will not be published
CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.

EDITORIAL OF THE DAY

  • Signalling good times, current account deficit is likely to grow from here on

    The current account deficit (CAD) numbers for April-June quarter declined sharply to 1.7 per cent of GDP.

FC NEWSLETTER

Stay informed on our latest news!

INTERVIEWS

GV Nageswara Rao

MD & CEO, IDBI Federal Life

Timothy Moe

Goldman Sachs

Chander Mohan Sethi

CMD, Reckitt Benckiser India

COLUMNIST

Arun Nigavekar

Disruptive innovation in education

The past two weeks had a fair share of interesting ...

Rajgopal Nidamboor

Regain the spirit of focused power

For aeons, the human race has been experimenting with a ...

Gautam Gupta

Manufacturing must keep workers’ welfare in mind

It may be early days yet, but the labour reforms ...

INTERVIEWS

William D. Green

Chairman & CEO, Accenture